11 Ways Architects Screw Up Construction Projects

The construction industry is perpetuated by a truly symbiotic process, in that all parties involved – project initiators, architects, engineers, contractors and more – rely on one another in order to achieve the best results possible. This coordinated effort is absolutely essential; the sum of all these parts equals a successful end product. That said, each one of these parties has the capability of completely ruining a construction project! In this 4-part series, we’re talking about how construction projects get screwed up. So what happens when Architects make a mistake? This article will be focused on 11 ways Architects screw up construction projects.


Check Out The Other Parts In Our “Screwed Up Construction” Series:

Part 1: Contractors | Part 3: Engineers | Part 4: Clients

Architects: What’s Good About Them

Let’s start with the positives! Here are a few good things to say about Architects:

  1. The First Ones On Board: When an initiator begins to plan a construction project, Architects are often the first ones they call. Architects have the burden of bringing the project from concept to a plan on paper, whilst dealing with the most amount of unknowns during this phase of planning.
  2. Big-Picture View: Architects are responsible for designing the building or structure on a big-picture level. This includes the overall appearance, required features and incorporating it into the surrounding area of the future site – all while accounting for codes, egress, standards, etc.
  3. They Must Understand Constructibility: While Contractors are the ones executing the physical work, Architects must have at least some working knowledge of constructibility and feasibility in design. This includes knowledge of manufacturers, means/methods and so on.

Now with that said, let’s get into it…

Disclaimer: I have a B.S. in Civil Engineering but have worked my entire career as a contractor. The content within this article is based on my anecdotal experiences working with architects and the feedback I get from others only.

Here Are 11 Ways Architects Screw Up Construction Projects:

  1. Leaving Design Details ‘To Be Coordinated’ By Contractors
  2. Not Using ‘Basis-Of-Designs’ When Designing & Specifying The Project
  3. Excessively Noting ‘Verify-In-Field’ On Drawings
  4. Not Considering Constructibility In Design
  5. Unclear Or Vague Design Specifications
  6. Delayed Review Or Approval Of Contractor Documents
  7. Changing Design While Project Is Underway
  8. Requesting Materials Or Building Components That Don’t Exist
  9. Inflexible In Design Specifications
  10. Untimely Review & Processing Of Contractor’s Requisitions
  11. Nitpicking Finished Products (‘Never Ending Punchlist’)

Note: There is a bit of overlap on this list between our engineer & architect articles in this four-part series. We will provide specific examples of each point listed to illustrate how each item applies in context.

1. Leaving Design Details ‘To Be Coordinated’ By Contractors

In part 1 of this series, we described the importance of contractors coordinating their work together onsite. When it comes to the means and methods of construction, contractors are certainly responsible for this.

This real issues begin to arise when contractors are expected to not only coordinate their work, but also coordinate the design details of how their work will interface with other adjacent finished products.

On some projects, the architect will not include any visuals of how a particular building detail is to look when constructed onsite, but will instead note that the details are ‘to be coordinated‘ between contractors, usually where multiple components come together. This is particularly common in instances where multiple contractors are required to submit shop drawings of their design for approval before work starts.

This isn’t wrong in all scenarios, as the architect may simply not have access to certain proprietary details of the contractors or manufacturers that provide the shop drawings. It also depends on how the contracts are written.

In many cases though, leaving excessive details ‘to be coordinated’ can lead to:

  1. Prolonged / additional reviews of shop drawings to further coordinate details, which can create schedule delays.
  2. Increase in RFI submissions.
  3. Confusion & installation issues in the field, which can in turn produce delay claims, change order requests, etc.

As they say, the best medicine is preventative. While leaving details ‘to be coordinated’ seems like it will save design costs/time up front, Architects make a mistake in many instances when they leave too many details unfinished.

Related: The Difference Between Shop Drawings And Construction Drawings

2. Not Using ‘Basis-Of-Designs’ When Designing & Specifying The Project

As a general rule of thumb, construction projects that run the smoothest are the ones that are set up right from the very beginning.

This places a lot of responsibility on the architect and other designers that get brought on board early. For this, they should be commended.

That said, there are some big missteps that can be taken during these early phases of a project. One of them, as discussed in section 1, is leaving finer details to be coordinated once contractors are on board. We covered a few of the many potential risks this presents.

One way Architects make a mistake early on in a project is by not using a Basis-of-Design.

In short, a Basis-of-Design (B.O.D.) is a making reference to a specific manufacturer, building system, product or even another completed project with similar features when designing a project on paper.

Using a Basis-of-Design is helpful in the following ways:

  • Understanding products that are actually on the market and usable.
  • Getting potential manufacturers/etc. on board early allows them to gain at least some momentum for if and when they’re hired for the project. This isn’t possible in all scenarios, but can be in some.
  • The architect can understand finer details in a more tangible way, while spotting any potential issues or items that require refinement.

Without B.O.D.s, contractors will be left figuring out these details later, which often leads to delays, change orders and constructibility issues.

Related: The Purpose Of Mockups In Construction & Why They’re So Important

3. Excessively Noting ‘Verify-In-Field’ On Drawings

The term ‘Verify in Field (VIF)’ refers to any dimension or condition in the design documents that is either not clearly defined, unknowable or is subject to change when the project gets going.

In fairness, an architect cannot always estimate exactly what the dimensions of a finished product will be, nor can they understand all of the conditions that will be present when work gets going.

Unfortunately, design documents can sometimes be riddled with ‘VIF’ comments to the point where contractors must make assumptions in the bidding and execution stages of the project. ‘VIF’ notations are sometimes used for bad reasons (queue the dramatic music). Here are a few:

  1. The architect is short on time: They must produce a design quickly, sometimes under constraint of a fixed budget. When time is short, Architects could end up marking ‘VIF’ of certain conditions simply because they don’t have time to dig deeper.
  2. Budget / due diligence is limited: Services like 3d computer modeling (BIM), site surveying, geological reports and feasibility studies are meant to provide valuable information about building conditions as an upfront investment. Unfortunately, the need for services like these are only seen in hindsight; services like this are oftentimes left out in order to ‘save money’ in the early planning stages of a project.
  3. Laziness: For lack of a better word, some architects may not wish to get down into the fine details to determine how certain conditions will look in the field and instead leave them to contractors. What’s the worst that can happen?

Architects make a mistake when leaving too many conditions to be verified in the field, as it can leave the project vulnerable to underestimated work/material quantities, unforeseen conditions and a host of other issues – all of which ultimately cost money and time.

Related: Avoiding Rework In Construction: 10 Common Causes & Solutions

4. Not Considering Constructibility In Design

Beautiful designs on paper are wonderful, but can they be brought to life?

This is the crux of a designer’s burden – optimizing appearance and feasibility. Making matters worse, many projects are often constructible as a whole, but certain elements of the project are not. Of course, even a few portions of the scope of work that run into constructibility issues can drag the whole project down with them.

Rather than talk about why architects make a mistake by not considering constructibility in their designs (fairly obvious), let’s talk instead about how constructibility can be considered:

  • Use Basis-Of-Designs For Building Systems & Materials: As described in section 2, a B.O.D. can remove a lot of the guesswork that designers have in terms of how components look and get put together.
  • Reference Other Projects: When something has been done before, it becomes a lot easier to determine if/how a particular building component comes together. Architects and design professionals can even consult the manufacturer, designer and/or installer from that other project.
  • Bring On Contractors Early: When considering constructibility of a project, why not ask the people who know how to put things together already? Bringing a contractor on board – particularly one with broad experience – to assist in the design phase of a project can eliminate a lot of these issues. The term used to describe this type of arrangement is known as Design-Build.

At the end of the day, the greatest looking, most state-of-the-art design is only as good as its’ ability to be built…within budget!

Related: How Do You Read Blueprints? Our Step-By-Step Guide With Examples!

5. Unclear Or Vague Design Specifications

This issue echoes similar sentiment to the points already covered, but in short – the more specific the specifications (heh) are on a project, the fewer questions and guesswork will be required.

The purpose of written specifications is to supplement design drawings with additional pertinent information. Some of the more important information contained in written specifications includes, but is not limited to:

  • Product Types/Grades/Etc. (Basis-of-Design)
  • Dimensional Tolerance Requirements For Finished Products
  • Applicable Building Codes & Regulations
  • Performance & Testing Standards
  • Required Warranties
  • Copies of Certifications & Similar Qualifications
  • Required Documents For Submission/Approval

If these topics are not clearly defined in the written specifications, it’s easy to imagine how a construction project can be screwed up as a result!

Related: What Are The Basics Of Project Scheduling? 9 Essential CPM Steps

6. Delayed Review Or Approval Of Contractor Documents

Schedule, schedule, schedule – everyone cares about getting the job done quickly, or at least on time. Therefore, any delay one or more parties may encounter on a project is never a good!

The review, response and approval of construction documents is no exception. Many architects make the mistake of taking too long to respond to documents that contractors submit for approval. Make matters more complicated, most project documents clearly state how long the design team has to respond to them once they’ve received a document.



PROMOTION



Because of this, it makes it more likely that contractors will point to this prolonged review as a delay, meaning a time extension request and everything that comes with it is more legitimate.

Of course, architects are by no means the only party capable of delaying a project, even in terms of submittals.

Related: The Construction Submittal Log: 5 Best Practices (FREE Excel Template)

7. Changing Design While Project Is Underway

For laughs, let’s use an example – a restaurant example.

Let’s say you sit down and order an appetizer and drinks at a restaurant, followed by an entree. It is very easy to know exactly what the price for the meal will be, and it’s somewhat easy to gauge how long the food will take.

Changing it up a bit. Let’s say that 10 minutes after you order an appetizer, you make a request for an alternative choice instead. The order for the original one was already placed so you now must buy both the original and the new appetizer. Seems reasonable, right?

You then make a change to the entree you selected as well – instead of cooking it medium, you decide on well-done. You also order an additional side dish.

It’s fairly obvious that the ‘revised’ meal will cost more than the original one. But now, the waitstaff spends more time and effort on your order and the kitchen spends more time coordinating the changes as well.

Now imagine debating the price of the second appetizer because it took longer and arrived at the same time as the main course. Imagine butting heads over how much longer the well-done meal takes compared to the original. In this dystopian world, tensions will flare over the amount of time the food takes as well as the total bill!

Meanwhile, food is no longer timed right, customers wait longer, the kitchen has unexpected delays and the waitstaff is running around more than expected.

This example is parabolic, but it illustrates the effect that changes have on the final end product, the end product’s price and the time it took to get there. Only in construction, the ‘tensions flaring’ isn’t dystopian – it’s reality!

As we can imagine, making changes to a building’s design once work is underway has a very similar effect on the construction schedule, timing/phasing of events, pricing, management and so on. Making design changes can be a big way architects screw up construction projects.

Related: What Should A Project Manager Do If The Customer Delays A Project?

8. Requesting Materials Or Building Components That Don’t Exist (Or At Least Aren’t Easily Found)

Building off of earlier sections, many design ideas sound great on paper but are not so great in reality. One way architects make mistakes in terms of budgeting and schedule is by expecting something completely custom that isn’t commonly found…without knowing it’s hard to get.

Of course, custom work is done all the time. So how is it that expecting custom items on a project is a mistake?

It’s not so much the custom aspect of it, but rather the research into:

  • What it’s going to take to get a custom item like that.
  • Who/where could it be made (think Basis-of-Design again).
  • The means in which a custom item could be made.
  • Is it even worth it, given the time and money it’ll take?

There are infinite anecdotal examples one could come up with to either justify the need for a ‘non-existent’ item vs. why it’s a bad idea. Generally speaking though, it’s not a great idea in terms of time or money to expect materials that are extremely hard to get unless the client has a surplus of both.

For example, I was involved in a structural steel project several years ago. A high-quality, top-of-the-line exterior coating was called for to recoat the original structural components that were still in good shape. The architect wanted a very specific color shade of paint.

The specified manufacturer (Basis-of-Design!) had about twenty stock colors that looked pretty close to the color the architect had in mind, but we ended up having to get a special batch mixed to match an exact color. A series of samples and mockups ensued. It ended up taking double the amount of time to get in comparison to the stock colors and costed a fair margin more per gallon than the stock colors, too.

Was it really worth the extra leg work? I don’t know. We got paid for it, at least.

Related: Procurement Strategy For Long Lead Items In Construction: A Few Tips

9. Inflexible In Design Specifications

A highly detailed, fully defined set of written specs is generally a good thing – it’s the opposite of what we discussed in section 5 earlier.

On the flip side, specifications that are too rigid can also be problematic.

What’s written in the specs is sometimes just not possible to achieve. It’s harder to prove this statement wrong than the contrary – the opposite being that the written specifications can never be wrong and they must be upheld no matter what.

The issue with unwavering written specifications is that they’re usually drafted early on in the project’s initiation phase, and the client comes to expect them as what they’re going to get when all is said and done. In turn, the architect or whoever else wrote the specs does their best to stick to exactly what they wrote.

They can’t always do so, though. The specs are typically modified out of necessity, not out of choice.

Here are some examples of work items I’ve managed that don’t (or can’t) comply with what’s written in the specs:

  • Custom-designed glass systems that cannot meet certain window performance standards.
  • Manufacturers unable to provide the level of warranty that’s expected.
  • Specified products that don’t work in all required conditions onsite.
  • Substituting one product for another due to availability.

There are other times when alternatives to what’s specified are objectively better for the project. This is when a stubborn designer is REALLY….fun to work with.

Related: Don’t Miss These Construction Management Rules Of Thumb & Hacks!

10. Untimely Review & Processing Of Contractor’s Requisitions

This one is not always architect’s faults – sometimes architects get assigned the role of owner’s representative in addition to design duty. This often includes the review and approval of contractor’s monthly requisitions.

Regardless of whether or not this responsibility is warranted, an untimely review and approval of monthly contractor’s requisitions does not help move the project along, to say the least. It’s made worse when these bills are overly scrutinized and reduced.

Of course, many contractors don’t bill the client correctly or fairly either.

Related: What Should Be Included In A Schedule Of Values? 7 Tips For Contractors

11. Nitpicking Finished Products (‘Never Ending Punchlist’)

Last on our list of ways architects screw up construction projects is by nitpicking the finished results. Said another way, finding fault in the work performed and requesting certain parts be redone over…and over….and over.

This is otherwise known as the “never-ending punch list“.

To be totally clear, we’re talking about work that’s otherwise within compliance of plans and specs. If a contractor installs subpar work, the architect has every right to demand it be redone, as does the client.

What we’re talking about here are the designers who just aren’t satisfied no matter what.

Some of this unnecessary criticism happens in the throes of the project, well before the end. That can be bad, but the worst part is the punch list work that takes place during the project’s close out, when everyone just wants to get the heck out off the job – including the client.

Punch list work holds up collecting final payments and extends the project indefinitely. Of course, if the work is within compliance, the architect or anyone else can’t just make a contractor do the work. It can go on and on for some time, though!

Related: 10 Things To Exclude From A Construction Bid, Proposal Or Contract



PROMOTION



11 Ways Architects Screw Up Construction Projects: In Summary

We’ve talked about the many possible ways that architects screw up construction projects, along with what happens when architects make a mistake. All that said, there are plenty of great architects and other design professionals that do excellent work and are essential in getting the project to a successful completion. On this website, we remove as much bias as possible and beat up on all parties equally! I hope this article has been helpful and informative – thanks for reading.

INDEX TAGS:

CLICK TO FOLLOW

“PM PROBLEMS” IS SUPPORTED THROUGH OUR PARTICIPATION IN SEVERAL AFFILIATE PROGRAMS. THIS INCLUDES THE AMAZON SERVICES LLC ASSOCIATES PROGRAM – AS AN AMAZON ASSOCIATE, WE EARN FROM QUALIFYING PURCHASES. WE MAY EARN A COMMISSION WHEN WE PROMOTE OTHER OFFERS FROM CLICKBANK, CJ, ASCEND & AD AGENCIES.  THROUGH THESE PROGRAMS, WE COLLECT FEES WHEN WE LINK TO PRODUCTS, SERVICES AND AFFILIATED WEBSITES. THE PRICE YOU PAY DOES NOT CHANGE IF BOUGHT THROUGH A LINK ON THIS WEBSITE. ALL PRODUCTS AND SERVICES RECOMMENDED WILL BE DIRECTLY RELATED TO THE CONTENT ON WHICH THIS SITE IS BASED. 

THE CONTENT ON THIS WEBSITE ORIGINATES FROM MY OWN PERSONAL KNOWLEDGE, EXPERIENCES AND JUDGEMENT [MY BACKSTORY]. OUR CONTENT IS DESIGNATED TO BE HELPFUL AND INFORMATIVE FOR OUR READERS, BUT IT IS NOT PROFESSIONAL, LEGAL, OR MEDICAL ADVICE! PLEASE SEEK OUT PERSONAL ASSISTANCE & ADVICE FROM A QUALIFIED PROFESSIONAL.

Leave a Reply

Your email address will not be published. Required fields are marked *

Share This Article

Is My Boss Manipulating Me? 12 Signs To Look For

Is My Boss Manipulating Me? Here Are 12 Signs Of A Manipulative Boss

Working in a toxic environment is what I consider a ‘silent killer’. Maybe you can relate to this. The effect settles in over time, not all at once. You start feeling less enthusiasm for your work. You start questioning you own abilities and skill. You take home a little more baggage with you each day. You’re working more to ‘keep up’. You feel worn out, tired, and Monday mornings are your worst enemy. You feel like you’re being drained of your life force one day at a time. Let’s get into the ways bosses manipulate employees, and what to do about them!

Read More »
What Do Building Inspectors Do? 4 Construction Inspector Responsibilities

What Do Building Inspectors Do? 4 Construction Inspector Responsibilities

We all know that buildings and structures are designed to meet certain standards. Whether they’re related to engineering requirements, material placement or building codes, it’s understood that contractors must adhere to strict guidelines when it comes to performing construction duties correctly. While owners and project initiators could simply trust that everything’s being built 100% correctly, the numerous construction disasters that’ve happened over the years prove just how costly – and even deadly – improper construction can be. Sure, there’s pretty much zero risk involved in painting a wall or putting down some new flooring, but projects that involve structural work, utilities, major alterations or public exposure must be monitored closely throughout the process to ensure that all work is being done correctly. That’s where building inspectors come into play. Let’s go through four key construction inspector responsibilities.

Read More »
Buying Materials For Contractors Directly? The Pros & Cons To Consider

Buying Materials For Contractors Directly? The Pros & Cons To Consider

When hiring a contractor, nearly everyone is looking for the same outcome: a successful completion of the work for the best (lowest) price possible. It’s instinctual for our minds to ponder how we can save money on the total cost of construction through whatever means possible. This commonly manifests itself through choosing the “cheapest” contractor right from the start, but there are many other ways that clients and general contractors alike try to save some cash when it comes to hiring contractors. One of these ways involves purchasing the materials directly, rather than leaving it to the contractor that’s being hired. Why? Markup. When we receive a proposal from a contractor, their price typically includes labor, equipment and material costs – all of which are then marked up higher to include the contractors’ overhead and profit margins. Clients can therefore save money by buying materials for contractors directly; if clients or general contractors buy the materials, the contractor (or subcontractor) won’t be able to charge overhead and profit on top of these material costs. This means the client gets to keep that money in exchange for buying the material themselves. That’s a big win…right? Well, that depends. While there are certainly some benefits to buying materials for contractors ourselves, there are also some potential drawbacks. Let’s go through the pros and cons!

Read More »
My Boss Doesnt Have My Back - What Should I Do My 5 Personal Tips

My Boss Doesn’t Have My Back: What Should I Do? My 5 Personal Tips

Do you ever feel betrayed by your boss? Does it seem like the two of you are always at odds, or that you simply can’t trust them? Unfortunately, this is something many of us can relate to. While we hope to have positive, productive relationships with our bosses, it’s certainly not a guarantee. Many of us feel like our bosses are only out for themselves – or even worse, working against us. In the land of the modern workplace and corporate culture, it can feel like work is just as much about office politics, individual advancement and covering our butts as it is about actually doing our jobs, and our bosses are no more exempt from this than we are. While our relationships with our bosses may feel worse in our minds than they really are, we may also notice certain patterns of behavior in them over time. Whether it be that our boss rarely offers us support, disagrees with us in front of others, throws us ‘under the bus’ or just plain doesn’t like us, we eventually reach the point where we think “My boss doesn’t have my back! What should I do?”. As someone who’s definitely been there, I’m happy to share with you the techniques I’ve used to mitigate this situation with success. Let’s get into them.

Read More »
Do Construction Managers Have To Travel? Lets Break It Down

Do Construction Managers Have To Travel? Let’s Break It Down

Let’s kick this one off with a bit of history. It’s the year 1848. Location? North America. What were folks up to? The Revolutionary War was over, but the Civil War had not yet begun. While I can’t speak for everyone since I wasn’t there, about 300,000 people decided to pack up their belongs, leave the family homestead and head to California, often on perilous journeys. The reason? The Gold Rush. Although gold had been discovered in California by local residents earlier, 1848-1849 is when the rush truly began to occur. Often referred to as ’49ers, people from all over the world began arriving in California – not only from the eastern parts of America, but also from Mexico, Peru, China, Australia, New Zealand, Europe and more. The prospects of wealth and prosperity – even through word of mouth and letters – was sufficient reason to give up everything, leave home and spend time digging or ‘panning’ for gold in the desert. In short, people wanted money and California was the best place to find it. While things in America are a bit more stable now, the idea of traveling to find prosperity is far from over – actually, that goes for any country of origin. While working from home is pushing things in a new direction, the prospect of traveling to find better opportunities is still relatable for millions of people. This group certainly includes people working in the construction industry, but there are many nuances to consider. If you came here after wondering “do construction managers have to travel?”, fear not – I aim to answer this with as much detail as I can.

Read More »
Writing Skills For Project Managers - These 6 Are Essential For Success

Writing Skills For Project Managers: These 6 Are Essential For Success

When one imagines a Project Manager, they may picture a person meeting with team mates, reviewing reports or giving presentations. While Project Managers do all of these things, there’s one task that nearly every P.M. spends quite a bit of time on, especially these days: writing. Whether it be writing letters or responding to endless emails, a significant portion of a Project Managers’ performance is underpinned by their ability to write. For many Project Managers (myself included), it takes years of time and experience to finely hone their writing skills. While the best way to get better at writing is to simply spend time doing it, there are many easy ways to improve writing abilities too; many of them are more about what not to do than anything else! Let’s talk about 6 essential writing skills for Project Managers that I’ve picked up over the years. Note that some of these tips aren’t necessarily about writing per se, but rather the intent and strategy behind why you should sometimes write a certain way. Let’s go!

Read More »
Tracking Construction Productivity - A Few Examples - Free Excel Template

Tracking Construction Productivity: A Few Examples [Free Excel Template]

Determining the profitability of a construction project is straightforward: it’s simply the difference between what a contractor gets paid to complete a project, less what it costs them to do so. When contractors create budgets for their projects, they have to estimate the cost and profit margin for every item of work they must perform. This includes materials, equipment, supplies, overhead expenses and of course – the cost of labor. Given that the vast majority of projects depend heavily on those who physically perform the work, it only makes sense that labor costs on most projects is substantial. It’s not uncommon for labor costs to make up the majority of a project’s total budget. The more efficient and productive the crews onsite work, the more profitable a project is. But how is this productivity calculated? How can construction managers and supervisors know whether or not the workers are meeting the budget? What if some items are going better than estimated, while others are doing worse? This is why tracking construction productivity on a regular basis is so important. Let’s go through a few examples of how to track construction productivity using an Excel template, which you can download for free below!

Read More »

6 Project Management Lessons From Enron & Their Historic Collapse

I just finished watching “The Smartest Guys In The Room”. It’s a documentary about Enron, the once-revolutionary Texas energy trading company that famously collapsed in 2001. From the early 90’s right up to their downfall, Enron was a darling of Wall Street, ranking #7 on the Fortune 500 in the same year that news of its’ massive accounting fraud and unethical business practices swept the world. In the summer of 2000, Enron’s stock hit an all-time high of over $90 per share. In late 2001, Enron filed for Chapter 11 bankruptcy and is still known as one of the largest corporate scandals in American history. Not only was Enron a business titan on Wall Street, but they were also well-known on ‘Main Street’ too. Enron’s collapse led to nearly 30,000 lost jobs, thousands of evaporated retirement accounts and countless investors left with worthless stock. Enron was once a (mostly) legitimate energy company before it essentially became an energy stock market in the 90s. What the heck happened? The Enron story is complex yet simple at the same time, unpinned by human ego, greed, deceit and pride. As for the specifics of what happened, we’ll get into those too. Let’s discuss six project management lessons from Enron and their demise that came to me after watching the film.

Read More »
6 Things I Learned While Working For A Failing Company

6 Things I Learned While Working For A Failing Company

Not all companies are meant to last unfortunately. Whether it be due to poor management, changing times, a rise in competition or even economic recession, many businesses end up closing their doors as the years go on. While some of these closures are sudden, other companies take several years before they’re completely shut down. As you probably know already, the daily experience employees have at a failing company is not always great – the atmosphere can range from unmotivated to extremely stressful and everything in between. This experience can also apply to your department or specific branch closing too, even if the company as a whole is not going out of business. If this is your experience, I can relate. The last two years at my previous company were spent seeing the ‘tidal wave’ coming in slow motion; most of us knew our division – once one of the largest in the company – would be shut down eventually given our overall performance, but no one knew exactly when. Here are six things I learned while working for a failing company that’ll hopefully be helpful!

Read More »
Is Project Management Competitive? The Answer Is Complicated

Is Project Management Competitive? The Answer Is Complicated

Many students and young professionals aspire to become a Project Manager at some point in their careers. Some of us desire the title and decision-making authority that being a P.M. provides, while others long to overcome challenges and deliver projects successfully. Of course, many of us want the higher salary and other financial perks that Project Managers often enjoy. Whatever your reason for wanting to become a P.M., it’s likely that other people out there also want to become a Project Manager for similar reasons. How many others are looking to become P.M.s? Is project management competitive? If you’re thinking about becoming a Project Manager and are looking for some stats, then read on!

Read More »
For Project Managers Becoming Entrepreneurs - 5 Tips From Experience

For Project Managers Becoming Entrepreneurs: 5 Tips From Experience

As we all know, project management is an exciting and dynamic field. There are plenty of ways we can challenge ourselves and continue to grow year after year. These are the aspects of project management that most of us love. As we gain experience, we learn a wide variety of skills in leadership, budgeting, scheduling, organization and more. If we can manage a decent-sized project, how much harder can it be to work for ourselves? After working as a Project Manager for awhile, you may begin to crave a challenge beyond what your typical position or company may offer. Perhaps you want to create a business from the ground up. Maybe you crave the ability to make your own schedule, or no longer answer to a boss. For many different reasons, there’s a growing percentage of working professionals who decide not to pursue their current career path anymore, and instead pursue the road less traveled…the path of the entrepreneur. Cue the dramatic music. There’s plenty of reasons why being ‘your own boss’ is great, but there are plenty of reasons one shouldn’t just dive in without preparation, either. I know because I’ve done it! At least to a certain extent. While I was prepared in some ways, there are several things I wish I understood much earlier – that’s what this article is about. For the project managers becoming entrepreneurs out there, let’s go over 5 tips based on my own experience, plus a little detail as to why I became an entrepreneur after thirteen years in construction management.

Read More »