CHECK OUT OUR YOUTUBE CHANNEL!

Basics Of Project Scheduling: Master These 9 Essential CPM Steps

As the old saying goes, a successful project comes down to getting three things right: cost, quality and time. Do that and you’re golden! Obviously, getting there is a little tougher than that. According to Mavenlink, 70% of projects fail. One of the biggest reasons for these failures is projects not finishing within the expected timeframe. With this is mind, developing a realistic and logistically-sound schedule for any project is essential. If you’re taking on a new project or will be soon, you might be wondering “what are the basics of project scheduling?” to avoid delays. In this article, we’ll walk through the essential steps needed to draft a project schedule. Let’s dive in.

Important Project Management Scheduling Terms

Before we walk through the basics of project scheduling, we must define a few terms. Here are a few key terms and definitions related to project scheduling:

  • Duration: How Long A Task Or Project Will Take.
  • Critical Path: The Sequence Of Tasks, And Their Durations, That Must Happen To Get The Project Done.
  • Milestones: The Date Of Which A Goal Or Specific Outcome Is Reached.
  • Lead Time: How Long An Item Or Deliverable Will Take To Get.
  • Predecessor: A Task That Must Be Completed Before Another Can Begin.
  • Successor: A Task That Must Come After Another Task Is Complete.

A Scheduling Metaphor…

A schedule can seem daunting when just starting out. Basically, we must walk away with a sequenced, accurate summary of how the project will happen on paper – step-by-step. When we set out to do this, though, we have nothing but raw data. Going from point A to point Z is a marathon.

I’m a big fan of metaphors and visual representations to get a point across. Here’s one that helps me….

When putting together a schedule, think like you’re sculpting a statue from a big block of stone.

At the beginning, we aren’t worried about sculpting out the nose on the statue’s face – we’re just trying to get some rough parameters established to begin forming the statue’s body. We first must chip away excess stone in areas it’s clearly not needed, then worry about getting the details right.



PROMOTED



The finer details come later – the large but less refined steps come first.

How To Put Together A Project Schedule Using The CPM Scheduling Method

Basics Of Project Scheduling: Create A Schedule Using CPM

In this example, we will explore the steps needed to draft a project schedule using the CPM, which stands for Critical Path Method.

When drafting a schedule for a project, it’s important to follow specific steps in order to take all of the information into consideration. Below are the steps necessary to draft a project schedule using the CPM, in the same sequence we’d sculpt the statue above – biggest to smallest. Click to jump to a specific section:

  1. Identify Fixed Variables & Restrictions
  2. Make Note Of & Quantify Long Lead Items
  3. Identify The Order Of Events aka ‘Sequence’
  4. Once A Sequence Is Established, Tasks Must Be Prioritized Using Predecessors & Successors
  5. After Prioritizing Tasks, Identify The Tasks On The ‘Critical Path’
  6. Calculate The Duration Of The Critical Path Items
  7. Identify Milestones In The Schedule
  8. Factor In Possible Overlap On The Project Schedule
  9. Fit In The Non-Critical Path Items
  10. Basics Of Project Scheduling: Additional Tips

We’ll get into the steps below using the construction of a house to create a sample project schedule. Scroll for more!

1. Identify Fixed Variables & Restrictions

Necessary completion dates, weather restrictions, testing requirements, limited resources & other limiting factors will dictate the parameters for which the schedule must fit within.

Below is a table of some fixed variables and restrictions for our house construction example:

Task Description
Required Completion Date
Signed Auth. For Contractor To Proceed
March 1st, 2019
Officially Break Ground
May 1st, 2019
Concrete Foundation Reaching Full Stren.
June 30th, 2019
House Is Air- & Water-Tight
October 31st, 2019
Move-In Ready
December 31st, 2019

These are key dates that the schedule must accommodate. Now that we’ve identified the project’s fixed dates and restrictions, we can move onto step 2.

2. Identify & Quantify Long Lead Items

Certain tasks will have a Long Lead Time associated with them. This is the time it takes to order & receive a physical item, or the time it takes to complete a process or service. Certain building materials take a long time to get in-hand, as does a complex design from a professional.

Here are just a few long lead items in our hypothetical home construction example:

Item Description
Lead Time
Building Permit Approval
4 Weeks
Foundation Contractor’s Req. Notice
2 Weeks
Cust. Cabinets & Granite Countertops
6 Weeks
Roofer’s Required Notice To Begin
2 Weeks
Plumbing & Electrical Insp. & Sign-Off
3 Weeks
Final Building Inspection
2 Weeks

3. Identify The Order Of Events aka ‘Sequence’ Using A Flowchart

Which tasks must be finished before others can begin? A simple example is building a house – the roof can’t be built before the walls! The walls can’t be built before there’s a foundation. Items must come together in a certain sequence, regardless of time.

Here is a sample project schedule flow chart used to develop a sequence of events:

A Sequence Flow Chart Example For Project Scheduling

4. Prioritize Tasks Using Predecessors & Successors

As said above, certain tasks cannot begin until others end. The task that must happen BEFORE another is called a Predecessor, whereas a task that must happen AFTER another is called a Successor.


Below is a table of tasks from our house construction example, along with their various predecessors and successors:

Item/Phase Desc.
Predecessor Tasks
Successor Tasks
Design & Permitting
N.T.P.
Order Materials, Foundation Work
Excavation
Permit Approval
Foundation Work
Foundation Work
Permit Approval
Framing
Exterior Framing
Foundation
Waterproofing, Int. Framing
Waterproofing
Ext. Framing
Sheetrock, Windows, Siding
Int. Finishes
Air/Water-Tight
Punchlist & Sign-Offs

5. Identify The Tasks On The ‘Critical Path’

The Critical Path contains the key project steps that must happen in a particular order. Other non-critical items can be adjusted accordingly; they can happen independent of these critical path steps. The critical path items and the time they take are the backbone of a project schedule. The project’s time from beginning to end is almost always the time between the first critical path item starting, and the final critical path task ending.

In our house construction example, we’ve highlighted the steps we’ve decided to call the critical path items:

A Sequence Flow Chart & The CPM Critical Path Steps

6. Calculate The Duration Of The Critical Path Items

A key factor in scheduling is obviously time. A project’s duration – the time it takes – is almost always the duration of the critical path. Assigning a duration to each critical path item after considering all restrictions & fixed variables is the most crucial step to calculating a project’s completion time.

Here is a basic example of critical path items in our house schedule , which totals to the approximate total project duration. These are for example purposes only!

Critical Path Item Description
Duration
Design & Filings
8 Weeks
Permit Approval
4 Weeks
Excavation / Foundation
4 Weeks
Ext. Framing, Roofing & Waterproofing
8 Weeks
Sheetrock & Prep
3 Weeks
Utilities – Plumbing, Elec., Etc.
4 Weeks
Kitchen, Bathrooms, Sinks, Appliances
6 Weeks
Final Inspections & Sign-Offs
4 Weeks
TOTAL
41 Weeks

7. Identify Milestones In The Schedule

Milestones are dates when a specific goal or outcome has been reached. A milestone can be the completion of a task on the critical path, or a date involved with a specific restriction or fixed variable (step 1). By making sure that each milestone is reached, a project manager is keeping the entire project on track.

As we mentioned earlier, milestones can be reaching fixed dates or specific critical goals. In our house example, this includes having the plans approved/permitted, pouring the foundation, having the house framed, getting the interior air/water-tight, utilities completed/signed off, etc.



PROMOTED

Save up to $300 on Open Box Products from Herman Miller, Steelcase, Haworth and more while supplies


8. Factor In Possible Overlap On The Project Schedule

Sometimes, the timeline of critical path tasks can be consolidated to shrink the overall schedule duration. This is often done by breaking these tasks into smaller tasks and figuring out which of them could start while the main task’s predecessor is still going.

9. Fit In The Non-Critical Path Items

The less critical items can now be scheduled around the critical ones. If a task can happen within a range of dates but takes a lot less time than given, this task has float associated with it. If a one month window of time is available for a task that takes one week, then the task has a few weeks of float to play with.

Basics Of Project Scheduling: Some Additional Tips

Thanks for reading this far! We’ve now reviewed the process of drafting a project schedule and all of the steps that go with it.

Here are a few additional tips to consider when drafting your next schedule:

  • Request lead times and estimated timeframes from any consultants and contractors when first requesting a price.
  • Similarly, make clear any fixed variables and deliverable dates when requesting a price.
  • Always add a contingency to each task’s expected duration.
  • Factor in revisions and typical delays while creating the initial schedule.
  • Specifically identify milestones on the critical path, along with all of the predecessors for each phase. This makes clear what is most important to achieve during the vital phases of the project

The Basics Of Project Scheduling In Summary

This article has covered all of the basic knowledge needed to begin creating project schedules. If you came here wondering “What Are The Basics Of Project Scheduling?“, you now have a solid understanding of project scheduling terminology and the 9 key steps to follow when creating a CPM-based project schedule! Thanks again for reading!

INDEX TAGS:

CLICK TO FOLLOW

“PM PROBLEMS” IS SUPPORTED THROUGH OUR PARTICIPATION IN SEVERAL AFFILIATE PROGRAMS. THIS INCLUDES THE AMAZON SERVICES LLC ASSOCIATES PROGRAM – AS AN AMAZON ASSOCIATE, WE EARN FROM QUALIFYING PURCHASES. WE MAY EARN A COMMISSION WHEN WE PROMOTE OTHER OFFERS FROM CLICKBANK, CJ, ASCEND & AD AGENCIES.  THROUGH THESE PROGRAMS, WE COLLECT FEES WHEN WE LINK TO PRODUCTS, SERVICES AND AFFILIATED WEBSITES. THE PRICE YOU PAY DOES NOT CHANGE IF BOUGHT THROUGH A LINK ON THIS WEBSITE. ALL PRODUCTS AND SERVICES RECOMMENDED WILL BE DIRECTLY RELATED TO THE CONTENT ON WHICH THIS SITE IS BASED. 

THE CONTENT ON THIS WEBSITE ORIGINATES FROM MY OWN PERSONAL KNOWLEDGE, EXPERIENCES AND JUDGEMENT [MY BACKSTORY]. OUR CONTENT IS DESIGNATED TO BE HELPFUL AND INFORMATIVE FOR OUR READERS, BUT IT IS NOT PROFESSIONAL, LEGAL, OR MEDICAL ADVICE! PLEASE SEEK OUT PERSONAL ASSISTANCE & ADVICE FROM A QUALIFIED PROFESSIONAL.

Leave a Reply

Your email address will not be published. Required fields are marked *

Share This Article