Long Lead Items: Procurement Tips In Construction & Project Management

On construction projects of all sizes, maintaining the schedule is paramount. While most projects experience some level of delay, a construction project can be heavily impacted, derailed and even cancelled when certain items in the scope don’t go as planned. This includes items with a long lead time – items that take a long time to actually get in hand. It’s extremely important that long lead items run smoothly through their entire process; from procurement to installation. In this article, we’re breaking down the procurement strategy for long lead items in construction, along with a few tips to consider!

Jump To Section:

What Are Some Examples Of Long Lead Items?

As we stated earlier, a long lead item in construction is anything that’ll take a relatively long time to take place after the initial request is made.

What’s a long time? Opinions on this varies, but in my opinion, I consider any item that takes more than one week to get as a ‘long lead item‘.

While the one-week time period can serve as a benchmark, it’s important to remember that some items will take weeks, months or even years to be fully, 100% delivered.

Long lead items can also require heavy coordination, take place over multiple phases of work and represent a considerable dollar value.

Here are a few examples of long lead items in construction:

  • A contractor or service that must be scheduled to work several weeks in advance, with little room for change or adjustment after the fact.
  • A piece of specialty equipment that’s in high demand or hard to get.
  • Materials that are not commonly used or stocked regularly.
  • Custom-fabricated items: there are truly too many examples to list, but some I’ve personally procured include exterior facade systems, stonework, stainless steel building components, ornamental sheet metal, bridge deck panels, guardrails and many more.

There are so many different types of long lead items in construction – these are just a few examples.

With the risk surrounding long lead items, it makes sense to prepare for them as much as possible at the beginning of the project. That said, long lead items matter throughout all phases of any type of project, as they have the ability to effect the project’s overall outcome to such a high degree.

Let’s talk about how to handle long lead items throughout each key project phase.

Long Lead Items During Planning Stage

When any project is in the conception stage, it’s difficult to clearly imagine what the end of the project will look like, at least in terms of how to make it happen. Owners and initiators know what they want, but they don’t know what exactly needs to happen along the way.

By identifying items with a long lead time, Owners and Designers alike will at least have an understanding of the project’s overall timeframe.

On larger projects, this doesn’t usually apply to items that take just a week or two to get. When a certain element of a project requires several months of lead time, such a factor can drastically impact how the project will proceed. Expectations can then be set properly.

For example: Consider a high-rise building that features an all-glass curtainwall. That curtainwall system won’t even BEGIN to arrive onsite for several months after a Purchase Order is signed, shop drawings are approved and a deposit is paid – it must be ordered well in advance.

Owner and Designer expectations must align with this from the get-go.

Read Next: What Should A Project Manager Do If The Customer Delays A Project?

Long Lead Items During Estimating & Bidding Stages

When contractors assemble a bid for a project, they must consider several variables. This includes the overall timeframe of a project, but also the ebb and flow of how the work will proceed:

  • Do they need to frequently mobilize and demobilize?
  • Will there be a bit of work up front, then six months of silence before the project resumes?
  • How long with the project take overall?
  • Which items fall on the critical path?

As you can imagine, the lead time of labor, equipment, materials, etc. all affect the answers to these questions.

Continuing our high rise curtainwall example from above, that contractor may be required to mobilize, take dimensions of the concrete or steel structure, supply them to the curtainwall manufacturer, then demobilize for several months until the curtainwall deliveries start arriving.

This means the contractor will need to mobilize multiple times and find other work to do in between.

A different example: say a particular type of specialty paint takes four weeks to get. A contractor may elect to purchase a large amount of the paint all at one time, rather than in small batches. They may also elect to purchase a lot more of it to cover waste and mistakes than they otherwise would’ve.

This is simply because it takes so long for the paint to arrive that it’s best not to take the chance of ever running out.

These concerns of the contractor will manifest themselves at the time of bid via higher pricing, requesting an up-front deposit for the paint and other general approaches to the project too.

Read Next: How To Estimate Construction Costs: Our Comprehensive Guide

Long Lead Item Coordination

Projects with long lead items can quickly slam to a stop when all parties aren’t on the same page as to how these items must be handled. While it’s about as simple as that, here’s an example.

Suppose a project requires a specialty subcontractor to remove hazardous materials from the site. This company requires 30 days’ notice before they can start onsite to prepare, get permits, etc.. In this scenario:

The Owner must anticipate this amount of lead time in their expectations of overall project timeframes.

Design Professionals must understand what this contractor will require from them in the way of direction, information, impact to the rest of the structure, etc. Designers / Construction Managers must have this information available in the proper timeframe.

Other Contractors onsite – be they a General Contractor hiring the hazmat company or other contractors working alongside them – must know how this hazmat company will affect their work. All parties must also understand schedules, onsite storage, access to work and other coordination-related information. Contractors must anticipate the impact they’ll experience well before the hazmat company arrives onsite.

The flip side of the coin? Imagine if the client, designers, managers and general contractor don’t know that the hazmat contractor needs 30 days’ notice before the work will begin, or fully understand how their own work will affect the jobsite – they’re in for a rude awakening!

Read Next: How Do You Manage Subcontractors? 7 Essential Tips

Long Lead Item Procurement Risk Analysis

All construction projects carry risks.

Risk of not finishing on time, of being improperly built, of contractors going bankrupt, etc. are just a couple examples.

When a portion of work with a long lead time goes south, these effects are felt tenfold down the chain. It may delay the project by weeks or even months!

When procuring a long lead time item, it’s essential that owners, designers and contractors alike perform a risk analysis for that item.

A risk analysis in this context is more or less drafting a list of everything that could possibly go wrong with that particular item of work, and what will be done to address it.

Here are some good questions to ask when procuring a long lead item on a construction project:

  • Where does this item fit in the sequence of construction?
  • How will work that’s adjacent, on top of or underneath this particular item be affected?
  • What payments are needed to get this item onsite? When are payments needed?
  • Which parties need to coordinate and contribute to the procurement of this item?
  • What approvals are required for this item to move forward?
  • Can any aspects of a custom-made component be field-modified in the event of an issue? What field modifications may be required?

Preparedness is one of the most important aspects of completing a construction project successfully.

Thoroughly vetting and planning the procurement of long lead items is one way to avoid costly mistakes.

Read Next: What Are The Basics Of Project Scheduling? 9 Essential CPM Steps

Long Lead Item Execution & Monitoring

Last but not least, it’s vital that all long lead items are executed properly and monitored to completion.

Until a long lead item is completely done, it must be monitored closely – the risks surrounding items like these are so plentiful that one misstep could derail the whole item of work.

When procuring long lead items in construction, one must establish milestones throughout the process. This allows all parties involved to understand what needs to happen one step at a time.

Here’s an example. Suppose a new bridge deck is going to be pre-fabricated in a shop setting [a la Fast 14 in Boston].

Imagine that the concrete substructure will be built in the field, whereas the bridge deck will be transported onto the roadway and set into place by crane.

The fabrication for this bridge will begin two months before it will arrive onsite.

Here are some typical milestones for a project like this:

  1. Achieve A Final Engineered Design
  2. Consider Means & Methods Of Installation:
    • Type Of Truck To Transport
    • Type Of Crane To Set The New Deck
  3. Commence Fabrication, Including Deposits, Signing A Contract, Etc.
  4. Construct The Concrete Substructure & Ensure It’s Built To Tolerance
  5. Procure Hardware & Materials Required To Set The Deck, Like Bolts, Anchors, Bearing Pads, Etc.
  6. Achieve Adequate 28-Day Concrete Strength Of The Substructure
  7. Achieve Adequate 28-Day Concrete Strength Of The Bridge Deck
  8. Bridge Deck Is 100% Complete For Installation
  9. Schedule Trucking & Crane/Hoisting Services For Install
  10. All Material Is Procured & Onsite
  11. Bridge Deck Is Transported, Hoisted & Set Into Place
  12. Bridge Deck Is 100% Installed

Just like managing a large, complex project, setting intermittent milestones is essential to keeping long lead items on track!

Read Next: Avoiding Rework In Construction: 10 Common Causes & Solutions

Procurement Strategy For Long Lead Items In Construction: In Summary

While long lead items carry many types of inherent risk, there’s plenty we can do as Contractors, Design Professionals and even Owners to mitigate these risks on our projects. Most importantly – the more that can be done BEFORE any contracts are signed or work takes place, the better! I hope you’ve found this article helpful and informative. Thanks for reading.

INDEX TAGS:

CLICK TO FOLLOW

“PM PROBLEMS” IS SUPPORTED THROUGH OUR PARTICIPATION IN SEVERAL AFFILIATE PROGRAMS. THIS INCLUDES THE AMAZON SERVICES LLC ASSOCIATES PROGRAM – AS AN AMAZON ASSOCIATE, WE EARN FROM QUALIFYING PURCHASES. WE MAY EARN A COMMISSION WHEN WE PROMOTE OTHER OFFERS FROM CLICKBANK, CJ, ASCEND & AD AGENCIES.  THROUGH THESE PROGRAMS, WE COLLECT FEES WHEN WE LINK TO PRODUCTS, SERVICES AND AFFILIATED WEBSITES. THE PRICE YOU PAY DOES NOT CHANGE IF BOUGHT THROUGH A LINK ON THIS WEBSITE. ALL PRODUCTS AND SERVICES RECOMMENDED WILL BE DIRECTLY RELATED TO THE CONTENT ON WHICH THIS SITE IS BASED. 

THE CONTENT ON THIS WEBSITE ORIGINATES FROM MY OWN PERSONAL KNOWLEDGE, EXPERIENCES AND JUDGEMENT [MY BACKSTORY]. OUR CONTENT IS DESIGNATED TO BE HELPFUL AND INFORMATIVE FOR OUR READERS, BUT IT IS NOT PROFESSIONAL, LEGAL, OR MEDICAL ADVICE! PLEASE SEEK OUT PERSONAL ASSISTANCE & ADVICE FROM A QUALIFIED PROFESSIONAL.

Leave a Reply

Your email address will not be published. Required fields are marked *

Share This Article

Is My Boss Manipulating Me? 12 Signs To Look For

Is My Boss Manipulating Me? Here Are 12 Signs Of A Manipulative Boss

Working in a toxic environment is what I consider a ‘silent killer’. Maybe you can relate to this. The effect settles in over time, not all at once. You start feeling less enthusiasm for your work. You start questioning you own abilities and skill. You take home a little more baggage with you each day. You’re working more to ‘keep up’. You feel worn out, tired, and Monday mornings are your worst enemy. You feel like you’re being drained of your life force one day at a time. Let’s get into the ways bosses manipulate employees, and what to do about them!

Read More »
What Do Building Inspectors Do? 4 Construction Inspector Responsibilities

What Do Building Inspectors Do? 4 Construction Inspector Responsibilities

We all know that buildings and structures are designed to meet certain standards. Whether they’re related to engineering requirements, material placement or building codes, it’s understood that contractors must adhere to strict guidelines when it comes to performing construction duties correctly. While owners and project initiators could simply trust that everything’s being built 100% correctly, the numerous construction disasters that’ve happened over the years prove just how costly – and even deadly – improper construction can be. Sure, there’s pretty much zero risk involved in painting a wall or putting down some new flooring, but projects that involve structural work, utilities, major alterations or public exposure must be monitored closely throughout the process to ensure that all work is being done correctly. That’s where building inspectors come into play. Let’s go through four key construction inspector responsibilities.

Read More »
Buying Materials For Contractors Directly? The Pros & Cons To Consider

Buying Materials For Contractors Directly? The Pros & Cons To Consider

When hiring a contractor, nearly everyone is looking for the same outcome: a successful completion of the work for the best (lowest) price possible. It’s instinctual for our minds to ponder how we can save money on the total cost of construction through whatever means possible. This commonly manifests itself through choosing the “cheapest” contractor right from the start, but there are many other ways that clients and general contractors alike try to save some cash when it comes to hiring contractors. One of these ways involves purchasing the materials directly, rather than leaving it to the contractor that’s being hired. Why? Markup. When we receive a proposal from a contractor, their price typically includes labor, equipment and material costs – all of which are then marked up higher to include the contractors’ overhead and profit margins. Clients can therefore save money by buying materials for contractors directly; if clients or general contractors buy the materials, the contractor (or subcontractor) won’t be able to charge overhead and profit on top of these material costs. This means the client gets to keep that money in exchange for buying the material themselves. That’s a big win…right? Well, that depends. While there are certainly some benefits to buying materials for contractors ourselves, there are also some potential drawbacks. Let’s go through the pros and cons!

Read More »
My Boss Doesnt Have My Back - What Should I Do My 5 Personal Tips

My Boss Doesn’t Have My Back: What Should I Do? My 5 Personal Tips

Do you ever feel betrayed by your boss? Does it seem like the two of you are always at odds, or that you simply can’t trust them? Unfortunately, this is something many of us can relate to. While we hope to have positive, productive relationships with our bosses, it’s certainly not a guarantee. Many of us feel like our bosses are only out for themselves – or even worse, working against us. In the land of the modern workplace and corporate culture, it can feel like work is just as much about office politics, individual advancement and covering our butts as it is about actually doing our jobs, and our bosses are no more exempt from this than we are. While our relationships with our bosses may feel worse in our minds than they really are, we may also notice certain patterns of behavior in them over time. Whether it be that our boss rarely offers us support, disagrees with us in front of others, throws us ‘under the bus’ or just plain doesn’t like us, we eventually reach the point where we think “My boss doesn’t have my back! What should I do?”. As someone who’s definitely been there, I’m happy to share with you the techniques I’ve used to mitigate this situation with success. Let’s get into them.

Read More »
Do Construction Managers Have To Travel? Lets Break It Down

Do Construction Managers Have To Travel? Let’s Break It Down

Let’s kick this one off with a bit of history. It’s the year 1848. Location? North America. What were folks up to? The Revolutionary War was over, but the Civil War had not yet begun. While I can’t speak for everyone since I wasn’t there, about 300,000 people decided to pack up their belongs, leave the family homestead and head to California, often on perilous journeys. The reason? The Gold Rush. Although gold had been discovered in California by local residents earlier, 1848-1849 is when the rush truly began to occur. Often referred to as ’49ers, people from all over the world began arriving in California – not only from the eastern parts of America, but also from Mexico, Peru, China, Australia, New Zealand, Europe and more. The prospects of wealth and prosperity – even through word of mouth and letters – was sufficient reason to give up everything, leave home and spend time digging or ‘panning’ for gold in the desert. In short, people wanted money and California was the best place to find it. While things in America are a bit more stable now, the idea of traveling to find prosperity is far from over – actually, that goes for any country of origin. While working from home is pushing things in a new direction, the prospect of traveling to find better opportunities is still relatable for millions of people. This group certainly includes people working in the construction industry, but there are many nuances to consider. If you came here after wondering “do construction managers have to travel?”, fear not – I aim to answer this with as much detail as I can.

Read More »
Writing Skills For Project Managers - These 6 Are Essential For Success

Writing Skills For Project Managers: These 6 Are Essential For Success

When one imagines a Project Manager, they may picture a person meeting with team mates, reviewing reports or giving presentations. While Project Managers do all of these things, there’s one task that nearly every P.M. spends quite a bit of time on, especially these days: writing. Whether it be writing letters or responding to endless emails, a significant portion of a Project Managers’ performance is underpinned by their ability to write. For many Project Managers (myself included), it takes years of time and experience to finely hone their writing skills. While the best way to get better at writing is to simply spend time doing it, there are many easy ways to improve writing abilities too; many of them are more about what not to do than anything else! Let’s talk about 6 essential writing skills for Project Managers that I’ve picked up over the years. Note that some of these tips aren’t necessarily about writing per se, but rather the intent and strategy behind why you should sometimes write a certain way. Let’s go!

Read More »
Tracking Construction Productivity - A Few Examples - Free Excel Template

Tracking Construction Productivity: A Few Examples [Free Excel Template]

Determining the profitability of a construction project is straightforward: it’s simply the difference between what a contractor gets paid to complete a project, less what it costs them to do so. When contractors create budgets for their projects, they have to estimate the cost and profit margin for every item of work they must perform. This includes materials, equipment, supplies, overhead expenses and of course – the cost of labor. Given that the vast majority of projects depend heavily on those who physically perform the work, it only makes sense that labor costs on most projects is substantial. It’s not uncommon for labor costs to make up the majority of a project’s total budget. The more efficient and productive the crews onsite work, the more profitable a project is. But how is this productivity calculated? How can construction managers and supervisors know whether or not the workers are meeting the budget? What if some items are going better than estimated, while others are doing worse? This is why tracking construction productivity on a regular basis is so important. Let’s go through a few examples of how to track construction productivity using an Excel template, which you can download for free below!

Read More »

6 Project Management Lessons From Enron & Their Historic Collapse

I just finished watching “The Smartest Guys In The Room”. It’s a documentary about Enron, the once-revolutionary Texas energy trading company that famously collapsed in 2001. From the early 90’s right up to their downfall, Enron was a darling of Wall Street, ranking #7 on the Fortune 500 in the same year that news of its’ massive accounting fraud and unethical business practices swept the world. In the summer of 2000, Enron’s stock hit an all-time high of over $90 per share. In late 2001, Enron filed for Chapter 11 bankruptcy and is still known as one of the largest corporate scandals in American history. Not only was Enron a business titan on Wall Street, but they were also well-known on ‘Main Street’ too. Enron’s collapse led to nearly 30,000 lost jobs, thousands of evaporated retirement accounts and countless investors left with worthless stock. Enron was once a (mostly) legitimate energy company before it essentially became an energy stock market in the 90s. What the heck happened? The Enron story is complex yet simple at the same time, unpinned by human ego, greed, deceit and pride. As for the specifics of what happened, we’ll get into those too. Let’s discuss six project management lessons from Enron and their demise that came to me after watching the film.

Read More »
6 Things I Learned While Working For A Failing Company

6 Things I Learned While Working For A Failing Company

Not all companies are meant to last unfortunately. Whether it be due to poor management, changing times, a rise in competition or even economic recession, many businesses end up closing their doors as the years go on. While some of these closures are sudden, other companies take several years before they’re completely shut down. As you probably know already, the daily experience employees have at a failing company is not always great – the atmosphere can range from unmotivated to extremely stressful and everything in between. This experience can also apply to your department or specific branch closing too, even if the company as a whole is not going out of business. If this is your experience, I can relate. The last two years at my previous company were spent seeing the ‘tidal wave’ coming in slow motion; most of us knew our division – once one of the largest in the company – would be shut down eventually given our overall performance, but no one knew exactly when. Here are six things I learned while working for a failing company that’ll hopefully be helpful!

Read More »
Is Project Management Competitive? The Answer Is Complicated

Is Project Management Competitive? The Answer Is Complicated

Many students and young professionals aspire to become a Project Manager at some point in their careers. Some of us desire the title and decision-making authority that being a P.M. provides, while others long to overcome challenges and deliver projects successfully. Of course, many of us want the higher salary and other financial perks that Project Managers often enjoy. Whatever your reason for wanting to become a P.M., it’s likely that other people out there also want to become a Project Manager for similar reasons. How many others are looking to become P.M.s? Is project management competitive? If you’re thinking about becoming a Project Manager and are looking for some stats, then read on!

Read More »
For Project Managers Becoming Entrepreneurs - 5 Tips From Experience

For Project Managers Becoming Entrepreneurs: 5 Tips From Experience

As we all know, project management is an exciting and dynamic field. There are plenty of ways we can challenge ourselves and continue to grow year after year. These are the aspects of project management that most of us love. As we gain experience, we learn a wide variety of skills in leadership, budgeting, scheduling, organization and more. If we can manage a decent-sized project, how much harder can it be to work for ourselves? After working as a Project Manager for awhile, you may begin to crave a challenge beyond what your typical position or company may offer. Perhaps you want to create a business from the ground up. Maybe you crave the ability to make your own schedule, or no longer answer to a boss. For many different reasons, there’s a growing percentage of working professionals who decide not to pursue their current career path anymore, and instead pursue the road less traveled…the path of the entrepreneur. Cue the dramatic music. There’s plenty of reasons why being ‘your own boss’ is great, but there are plenty of reasons one shouldn’t just dive in without preparation, either. I know because I’ve done it! At least to a certain extent. While I was prepared in some ways, there are several things I wish I understood much earlier – that’s what this article is about. For the project managers becoming entrepreneurs out there, let’s go over 5 tips based on my own experience, plus a little detail as to why I became an entrepreneur after thirteen years in construction management.

Read More »